Architect Architects & Planners | TBP Architecture
Project Budget: $4,300,000
Funding Source: Measure A, Measure E, and Redevelopment Agency Fund
Completion Date: July 2017
The College Complex 2nd Floor Renovation project consists of converting temporary
Student Services swing space used during the Student Services Building Remodel project
back to instructional classroom and faculty office space. The project also includes
the modernization of the existing Business Department computer labs, classroom, and
offices. The project will create 9 classrooms, two of which will have the ability
to be used as a computer labs or regular classrooms. The project also creates 8 faculty
offices and 2 small conference rooms. Both sets of existing restrooms on the 2nd floor
will also be modernized and updated to meet current ADA standards.
Construction will begin in late December/Early January 2017. All construction activity will take place between 10:00pm and 7:00am to prevent disruption of any courses offered in the College Complex.