Construction Updates (as of May 16, 2012)

 

Timeline

Building for Sucess

Construction Timeline

Department

New/Interim
Facilities Space

Start Date

Estimated
Construction Completion Date

Estimated
Occupancy Date

 

Nursing / EMT

Old Science Area - Third Floor College Complex

December 2010

May 2012

Summer 2012

 

Business Services

Old Assessment Center - Third Floor College Complex

August 2011

May 2012

Summer 2012

 

Central Services

Classrooms 118 & 119 - First Floor College Complex

August 2011

May 2012

Summer 2012

 

Counseling*

English Classrooms 290, 291 & 292 - Second Floor College Complex

 

August 2011

 

April 2012

 

May 22, 2012

EOP&S, CalWORKs, DSP&S, Assessment and Career Centers, Student Services Admin.*

Old Math Area - Second Floor College Complex

August 2011

April 2012

Late May or early June,

except Assessment Moved May 14, 2012

Financial Aid/Employment Center*

Old Office of Instruction Building - Second Floor

August 2011

December 2011

January 3, 2012

Student Life

Old Graphic Arts Building

September 2011

December 2011

January 3, 2012

Admissions, Cashier, Information Center & Outreach*

Cafeteria

December 2011

April 2012

July 18, 2012

Transfer Academy

Business Area Room 239 - Second Floor College Complex

Spring 2012

August 2012

August 2012

Student Services Center

Student Services & Administration - Third and Fourth Floor College Complex

Fall 2012

Fall 2014

Spring 2015

 

* Swing Space until Student Services Center is completed