Construction Updates (as of May 16, 2012)
Construction Updates (as of May 16, 2012)
Department | New/Interim |
Start Date | Estimated | Estimated |
|---|---|---|---|---|
Nursing / EMT |
Old Science Area - Third Floor College Complex |
December 2010 |
May 2012 |
Summer 2012 |
Business Services |
Old Assessment Center - Third Floor College Complex |
August 2011 |
May 2012 |
Summer 2012 |
Central Services |
Classrooms 118 & 119 - First Floor College Complex |
August 2011 |
May 2012 |
Summer 2012 |
Counseling* |
English Classrooms 290, 291 & 292 - Second Floor College Complex |
August 2011 |
April 2012 |
May 22, 2012 |
EOP&S, CalWORKs, DSP&S, Assessment and Career Centers, Student Services Admin.* |
Old Math Area - Second Floor College Complex |
August 2011 |
April 2012 |
Late May or early June, except Assessment Moved May 14, 2012 |
Financial Aid/Employment Center* |
Old Office of Instruction Building - Second Floor |
August 2011 |
December 2011 |
January 3, 2012 |
Student Life |
Old Graphic Arts Building |
September 2011 |
December 2011 |
January 3, 2012 |
Admissions, Cashier, Information Center & Outreach* |
Cafeteria |
December 2011 |
April 2012 |
July 18, 2012 |
Transfer Academy |
Business Area Room 239 - Second Floor College Complex |
Spring 2012 |
August 2012 |
August 2012 |
Student Services Center |
Student Services & Administration - Third and Fourth Floor College Complex |
Fall 2012 |
Fall 2014 |
Spring 2015 |
* Swing Space until Student Services Center is completed